Engineering works in tanks erection in Aden Refinery, Yemen

Client:

Aden Refinery Company, A.R.C. , Aden, Yemen

 

Services Performed:

Errection of a 14 new tanks (fixed and floating roof) with a total capacity of 135000 cm

Repairing of a 17 tanks with a capacity of 320360 c.m.

Demolishment of 7 tanks with a capacity of 60000 c.m.

Design and errection of a LPG storage unit using 10 horizontal cylindrical  pressure vessels (bullet)

Pipelines with a total length of 21 km

Works during the main overhauls of refinery (Refinery Unit No.1  and No.2 Crude Unit)